Serverless

  • 1.  Meeting Minutes 29th July

    Posted Aug 08, 2022 07:09:00 AM
    Edited by Marina Bregkou Aug 08, 2022 07:18:13 AM
    Dear members,

    On the call on the 29th of July the working group specified that:
    • The Implementation of the NIST 800-53 controls to Serverless is done from the perspective of the TENANT. Hence, when a sub-control is not relevant it means that it is not relevant to the tenant.
    • Need to add another column to the spreadsheet and define where a control is to be deployed.
    • For the 2nd phase of our activity then, we will implement the controls form the CSP's perspective.
    • DEADLINE for this 1st phase will be the end of Q3: September 2022.
    Next working group call: Friday, 12 August, at 09:00 a.m. PST / 12:00 p.m. EST / 17:00 GMT / 18:00 CET.
    url: https://zoom.us/j/98681420926  (Meeting ID: 986 8142 0926)

    Kind regards,
    Marina


    ------------------------------
    Marina Bregkou,
    Senior Research Analyst,
    CSA
    ------------------------------